FAST PV in use on flat roofs and open areas

Get to know different areas of application and scenarios where FAST PV impresses – no drilling, quick installation and little personnel effort on site!


Photovoltaics on a flat roof of DTEC company, Spital am Pyhrn, AT

Power: 96 kWpeak 

Duration: 6 hours

Advantage: Cooperation with regional partners for the smooth processing of PV units, design, financing/funding and energy storage.

Before: Unused roof space on an industrial building

After: 96 kWpeak photovoltaic output


Photovoltaics in Waidhofen/Ybbs, Austria

Power: 300 kW photovoltaic power

Duration: 2 days in winter

Challenge: Open space that will be built on in about 2 years. The PV modules are then installed on the flat roof.


We simply need far fewer qualified staff and can complete several projects in a week. 

Electrical installer



Photovoltaics in Ybbsitz, Austria

Power: 273 kWpeak 

Duration: 1.5 days 

Challenge: Old roof that cannot be drilled into


Photovoltaic industrial roof, DB Schenker, Hamburg, DE

Power: 350 kWpeak
Duration: 1.5 days
Challenge: The assembly had to take place outside of the logistics company's operating hours. Thanks to the pre-assembly of the modules and the compact design, the photovoltaic system on the flat roof was able to take place over the weekend and operations could continue unhindered.


If installation has to be done quickly, FAST PV is the first choice!



Photovoltaics in Waidhofen/Ybbs, Austria

Power: 22 kW 

Duration: 1 hour 

Challenge: Manageable open space that needs to be used sensibly


Container roof

Power: 1.6-2.2 kWp possible depending on module performance
Duration: Depends on module size
Advantage: Can be used decentrally at any time; This means that each container becomes self-sufficient in 1 hour.