FAST PV in use on flat roofs and open areas
Get to know different areas of application and scenarios where FAST PV impresses – no drilling, quick installation and little personnel effort on site!
Photovoltaics in Waidhofen/Ybbs, Austria
Power: 300 kW photovoltaic power
Duration: 2 days in winter
Challenge: Open space that will be built on in about 2 years. The PV modules are then installed on the flat roof.
We simply need far fewer qualified staff and can complete several projects in a week.
Electrical installer
Photovoltaics in Ybbsitz, Austria
Power: 273 kWpeak
Duration: 1.5 days
Challenge: Old roof that cannot be drilled into
Photovoltaic industrial roof, DB Schenker, Hamburg, DE
Power: 350 kWpeak
Duration: 1.5 days
Challenge: The assembly had to take place outside of the logistics company's operating hours. Thanks to the pre-assembly of the modules and the compact design, the photovoltaic system on the flat roof was able to take place over the weekend and operations could continue unhindered.